Battery Replacement Procedu
Hello,
I will be replacing my house batteries this weekend. 1998 Featherlight Vantare. Two Trace 4024 inverters. 8 4D batteries. I just want to confirm the following the correct shut down / startup procedure. Please advise
Step One (inside coach inverter / breaker panel.
1) Turn inverters off
2) Turn DC Main off
3) Turn off all AC breakers
Step Two (outside inverter bay Vantare Panel)
1) Pull Distribution Panel Button to OFF
2) Leave on Alternator Disconnect Switch
3) Turn off 24 Volt feeder breakers to Inverter 1 and 2
4) Turn off inverter output breakers
Step 3 (Water Bay)
1) Turn off shore power breaker
Do I need to shut of the coach 24 and 12 volt mains?
I plan on marking all battery cables as I take them out.
Any advice will be much appreciated.
Thanks
-
Did you get show pricing from Truk for Lifelines?
Later
bv
Bernie & Deborah
2019 Marathon X3 #1291
2019 Intech Stacker